Hydrogen Test Cells Construction

image

Coventry University

Coventry

section-icon
Education

  • property type

    Hydrogen Test Cells Construction

  • project duration

    8 weeks

  • projectscope

    Design and construct 4 new Hydrogen Test Cells in a test laboratory in Coventry. The project involved working with high and low-pressure hydrogen and required modifications and upgrades to existing ventilation, gas detection, fire alarm, and BMS systems.

bg-shape

Challenges Faced

The construction of Hydrogen Test Cells presented several challenges, including:

  • Safety Concerns: Working with high and low-pressure hydrogen required rigorous safety measures.
  • System Integration: Upgrading existing systems for ventilation, gas detection, fire alarm, and BMS to accommodate the new test cells.
  • Regulatory Compliance: Ensuring compliance with safety and regulatory standards for working with hydrogen.

Our Solution

SMS was appointed to design and construct the Hydrogen Test Cells, implementing the following solutions:

  • Safety Protocols: Developed and implemented strict safety protocols for working with high and low-pressure hydrogen.
  • System Upgrades: Modified and upgraded ventilation, gas detection, fire alarm, and BMS systems to integrate seamlessly with the new test cells.
  • System Integration: Successfully integrated new test cells with existing ventilation, gas detection, fire alarm, and BMS systems
  • Minimised Downtime: Executed modifications and upgrades with minimal disruption to ongoing laboratory operations.
image
shape

sec-titleConclusion

SMS successfully designed and constructed four new Hydrogen Test Cells, demonstrating expertise in handling high and low-pressure hydrogen and upgrading existing systems for optimal performance. The project showcased our commitment to safety, efficiency, and client satisfaction in specialised laboratory construction.

CONTACT US

conclusion image

sec-titleWhy choose us

We specialise in seamlessly delivering innovative and efficient project solutions, ensuring optimal functionality and cost-effectiveness for our clients.

sec-titleWhy choose us

We specialise in seamlessly delivering innovative and efficient project solutions, ensuring optimal functionality and cost-effectiveness for our clients.

With the dust now settling on the completion of the C-ALPS Hydrogen Laboratory research project I would now like to extend my thanks and gratitude for the success of a most challenging project. With some client changes and the impact of the various supply chain materials issues this has not phased anyone and the testament to you all is the conclusion of a great project! Your dedication and persistence has ensured that a great team ethos has been fostered in concluding the work.

Just a quick note to say thank you for a great job, the job looks great and a big part of that look is down to the hard work of your staff who performed to the highest standards. Looking forward to working with the guys again.

Speller Metcalfe - DWP Luton Project

Savesta Construction Ltd was appointed as the Principal Contractor for the new £2.10m Dining Room and Science Classrooms extension project at Moseley Park School, Wolverhampton. From the reconciliation of their quotation and throughout the construction phase we found Staffordshire Mechanical Services Ltd to be engaged and proactive. Their representatives were always happy to engage with the design and progress meetings and provided valuable contributions where necessary. Their works were completed snag free, on time, within budget and without any accidents. Their final account was detailed and transparent resulting in it being promptly agreed. Given our experience, Savesta Construction Ltd

Savesta Construction Ltd, Moseley Park School

Just a quick note to thank you for a job well done. Please pass on my thanks to your team, the feedback is very positive and it looks like nobody has been working over the Easter break, perfect! Thanks again.

Sodexo

I would like to take this moment in time to say thank you to you and your chaps. You have done a great job here at Northampton and I look forward to working with you all again.

Client for DWP Northampton Project

SMS' approach to projects is the best I have personally encountered. Their attention to detail and firm understanding of Mechanical & Electrical systems gives total confidence in project delivery and ultimately client satisfaction.

Chapman BDSP

SMS Ltd were a new Company to us, via the Diocese. They were very professional in how they worked, and were very flexible in working around our school hours and holidays. We had new heating in our nursery, and they also helped out with other water / heating problems we had been incurring for numerous years. Of which, other companies had been unsuccessful. The staff and governors at the school were so pleased with their work that they have asked to include SMS Ltd in tender / quote process for additional work in and around school.

Holly Hill Primary School, Birmingham

image

This site uses cookies to improve your experience. By clicking, you agree to our Privacy Policy.